CompletedConstruction

SBQ Hinterland Phase 1

North East England

Project Description

Construction services comprising ground remediation and related earthworks operations.

Project Details

Project Type
Construction
Status
Completed
Estimated Value
1m-5m
Decision Date
9 August 2024
Start Date
10 April 2024
Completion Date
31 August 2024
Reference
STDC-PROC-0436
Region
North East England
Commissioning Body
TEES VALLEY COMBINED AUTHORITY