Back to Bam Nuttall Ltd
ApprovedConstruction

YNE CDF Went Outfall Design and Build

North West England

Project Description

This project has the primary objective of refurbishing the asset of Went Outfall through replacing the existing pair of timber tidal doors and hinges with new stainless-steel tidal doors and hinges, to sustain the standard of service (SOS), ensuring the doors can operate as designed, able to open and close to regulate water heights

Project Details

Project Type
Construction
Status
Approved
Estimated Value
1m-5m
Decision Date
24 October 2025
Start Date
4 November 2025
Completion Date
21 October 2026
Reference
CF-0558400D8d000003VQwdEAG
Region
North West England
Commissioning Body
Environment Agency

Data Source

This project was sourced from the UK Government Contracts Finder service, which publishes public sector contract awards.

View source

Worked on this project?

Share your experience working with Bam Nuttall Ltd on this or other projects.

Write a Review