Back to Jones Bros
CompletedInfrastructure

Cambridgeshire County Council A605 Kings Dyke Level Crossing Closure

East Anglia

Project Description

The Authority wishes to appoint a Provider for design and construction to bypass the level crossing at King's Dyke, Whittlesey. The works will include 1km of new road on structural embankments, a new bridge overthe railway and accommodating works. The scheme was previously awarded as a 2 stage Design and Buildcontract, for which a detailed design was completed. Cost estimates increased over time and so the Authority isnow seeking improved outcomes from the market. The Provider will be required to take responsibility for the existing detailed design, but may seek approval fromthe Authority as to where it may be improved. The Authority therefore welcomes Value Engineering exercisesfrom the Provider but notes that existing planning consent, site and technical constraints must be all upheld inany proposals which may come forward. Non-Material Amendments may be considered. It is expected that a contract will last for a period of approximately 2 years. To express interest in this opportunity Potential Providers should visit https://procontract.due-north.com/Advert?advertId=3e51e45c-c3c0-e811-80ef-005056b64545.

Project Details

Project Type
Infrastructure
Status
Completed
Estimated Value
10m-20m
Decision Date
5 May 2020
Start Date
18 May 2020
Completion Date
17 May 2022
Reference
LGSS001-DN424702-50845788
Region
East Anglia
Commissioning Body
LGSS Procurement on behalf of Cambridgeshire County Council

Data Source

This project was sourced from the UK Government Contracts Finder service, which publishes public sector contract awards.

View source

Worked on this project?

Share your experience working with Jones Bros on this or other projects.

Write a Review
    Cambridgeshire County Council A605 Kings Dyke Level Crossing Closure | Jones Bros | Construction Rating