Back to Octavius Infrastructure
CompletedConstruction

CP2551-24 G5-3_DCC_036 - Dinan Way Extension

Greater London

Project Description

This is a call off contract under the Generation 5 Civil Engineering, Highways and Transportation Infrastructure Works Framework 2024-2028 Lot 3. The scheme will consist of a 6.5m wide carriageway approximately 830m long from the junction of Dinan Way/Hulham Road to the A376 Exmouth Road. At each end of the proposed Dinan Way Extension the junction will take the form of a 3 and 4 arm compact roundabout. A new 2m wide shared pedestrian and cycle path along one side of the Dinan Way Extension will provide a facility for sustainable modes of transport from new developments and the northeast of Exmouth to access the Exe Estuary Trail. Two SUDS (consisting of filter drains, ditches and 5 ponds) will sustainably manage the surface water generated from the site and discharge into the Wotton Brook to the north. Various access points, maintenance bays and an agricultural crossing point are to be included.

Project Details

Project Type
Construction
Status
Completed
Estimated Value
5m-10m
Decision Date
19 November 2024
Start Date
19 November 2024
Completion Date
19 December 2025
Reference
DVNCC001-DN738440-04636940
Region
Greater London
Commissioning Body
Devon County Council

Data Source

This project was sourced from the UK Government Contracts Finder service, which publishes public sector contract awards.

View source

Worked on this project?

Share your experience working with Octavius Infrastructure on this or other projects.

Write a Review
    CP2551-24 G5-3_DCC_036 - Dinan Way Extension | Octavius Infrastructure | Construction Rating