Back to QTS Group
CompletedConstruction

Cliff Stabilisation of Freshwater Quarry Brixham

South West England

Project Description

A Geotechnical inspection assessed Freshwater Quarry to require rock stabilisation works. This contract will address the issues raised.

Project Details

Project Type
Construction
Status
Completed
Decision Date
15 December 2016
Start Date
16 January 2017
Completion Date
15 May 2017
Reference
T01416CCS
Region
South West England
Commissioning Body
Torbay Council

Data Source

This project was sourced from the UK Government Contracts Finder service, which publishes public sector contract awards.

View source