Caroline Street Flood Alleviation Works
Greater London
Project Description
In July 2019, heavy storms caused many houses in the Caroline Street, Sunderland to internally flood. Investigation into the area showed that the existing combined drainage system that takes the surface water is over capacitated and therefore means that the area floods whenever there is a heavy rainfall. A new Surface Water drainage system is to be installed to deal with the heavy rainfall.
Project Details
Project Type
Construction
Status
Completed
Estimated Value
500k-1m
Decision Date
28 June 2024
Start Date
1 July 2024
Completion Date
20 December 2024
Reference
SUN001-DN724737-82018606
Region
Greater London
Commissioning Body
Sunderland City Council
Other Projects by Rainton Construction
A684 Conyers Lane & C29 Arkengarthdale
North West England
Darlington BC - Various Locations within the Borough of Darlington - Carriageway Patching Prior to Preventative Maintenance 2026.
North East England
View all projects by Rainton Construction
UnlockData Source
This project was sourced from the UK Government Contracts Finder service, which publishes public sector contract awards.
View sourceWorked on this project?
Share your experience working with Rainton Construction on this or other projects.
Write a Review