Administration · 22 July 2021
Cleveland Bridge UK
Specialist trade · Darlington · North East England
What happened
CLEVELAND BRIDGE UK LIMITED (company number 03749601), incorporated in 1999, entered administration on 22 July 2021. Its status at Companies House is now: administration.
Why it failed
Covid delayed contract starts and added costs, an estimating error erased one project's margin and steel prices rose; working capital ran short and the Saudi parent declined further funding.
- Main reason: Covid-19
- Delays
- Losses on contracts
- Cost inflation
- Cash flow
- Funding withdrawn
- Group company failed
Our summary of the reasons given in the administrators' proposals. These record the administrators' and directors' account of what happened.
An administrator, a licensed insolvency practitioner, takes control of the company to try to rescue it, sell the business or get a better result for creditors than a liquidation.
Previously known as: CLEVELAND BRIDGE GROUP LIMITED, FAREACE LIMITED.
Timeline
The last accounts and payment report before the failure, then what happened, with the time between each.
30 December 2019
Last accounts filed were made up to this date
19 months later
22 July 2021
Administration started
AccountsPayment reportInsolvency
Before it failed
Key figures
- Owed to unsecured creditors (estimated), as at 9 September 2021
- £15.1m
- of which trade creditors £8.0m. about 267 creditors. a further £2.2m owed to its lenders. Expected return to unsecured creditors: none expected
- Administrators' proposals
The last accounts filed were full accounts made up to 30 December 2019, 19 months before it went into administration.
The full filing history, including any late filings, charges and director changes, is on Companies House.
Lessons learned report
We're writing plain-English reports on major construction failures: who was involved, why it happened, the warning signs and how long they were visible, and what to look out for next time.
Sign up to be told when reports are outIn the news
- Cleveland Bridge administration extended as Sri Lankan debt remains unpaid
Construction News · 1 September 2026
- Cleveland Bridge collapsed owing creditors £21m
Construction News · 15 September 2021
- Cleveland Bridge to shut after failing to secure buyer
Construction News · 10 September 2021
- Cleveland Bridge sets reopening date
Construction News · 6 August 2021
- Cleveland Bridge staff angry as a quarter are made redundant
Construction News · 5 August 2021
- Cleveland Bridge to restart production as sale effort continues
Construction News · 2 August 2021
- Cleveland Bridge collapse blamed on pandemic
Construction News · 22 July 2021