Administration · 24 June 2021

Nobles Construction

Main contractor · Liverpool · North West England

Share

What happened

NOBLES CONSTRUCTION LIMITED (company number 03068666), incorporated in 1995, entered administration on 24 June 2021. Its status at Companies House is now: liquidation.

Why it failed

Disputes absorbed management time and adjudication awards in its favour stayed unpaid; Covid-19 site closures added delays, and under creditor pressure the directors stopped trading in April 2021.

  • Main reason: Clients not paying or failing
  • Legal claims
  • Covid-19
  • Delays

Our summary of the reasons given in the administrators' proposals. These record the administrators' and directors' account of what happened.

An administrator, a licensed insolvency practitioner, takes control of the company to try to rescue it, sell the business or get a better result for creditors than a liquidation.

Timeline

The last accounts and payment report before the failure, then what happened, with the time between each.

  1. 30 March 2019

    Last accounts filed were made up to this date

    2 years later

  2. 24 June 2021

    Administration started

    10 months later

  3. 28 April 2022

    Winding-up petition presented

    2 months later

  4. 14 June 2022

    Winding-up order made by the court

  5. 21 June 2022

    Administration ended

AccountsPayment reportInsolvency

Before it failed

Key figures

Turnover in its last accounts, year to Mar 2019
£24.6m
Accounts at Companies House
Profit before tax, year to Mar 2019
£210k
Accounts at Companies House
Net assets, year to Mar 2019
£859k
Accounts at Companies House
Owed to unsecured creditors (estimated), as at 30 July 2021
£5.6m
of which trade creditors £4.3m. HMRC owed £321k. staff owed £595k. a further £191k owed to its lenders. Expected return to unsecured creditors: uncertain
Administrators' proposals

The last accounts filed were full accounts made up to 30 March 2019, 27 months before it went into administration. Private companies have nine months after their year end to file, so a gap of more than 21 months usually means the next accounts were overdue, one of the warning signs worth checking for.

The full filing history, including any late filings, charges and director changes, is on Companies House.

Lessons learned report

We're writing plain-English reports on major construction failures: who was involved, why it happened, the warning signs and how long they were visible, and what to look out for next time.

Sign up to be told when reports are out

In the news

We haven't matched any press coverage to this company yet. Search the news for Nobles Construction.