Administration · 6 February 2024
Readie Construction
Main contractor · London · Greater London
What happened
READIE CONSTRUCTION LIMITED (company number 06069233), incorporated in 2007, entered administration on 6 February 2024. Its status at Companies House is now: administration.
Why it failed
Fixed-price contracts were hit by post-Covid and Ukraine war inflation and subcontractor failures; sureties, banks and a client then withdrew support, leaving an unfillable cash gap.
- Main reason: Cost inflation
- Losses on contracts
- Covid-19
- Cash flow
- Funding withdrawn
- Clients not paying or failing
- Delays
- Market downturn
- Sale or investment failed
Our summary of the reasons given in the administrators' proposals. These record the administrators' and directors' account of what happened.
An administrator, a licensed insolvency practitioner, takes control of the company to try to rescue it, sell the business or get a better result for creditors than a liquidation.
Timeline
The last accounts and payment report before the failure, then what happened, with the time between each.
30 September 2021
Last payment practices report ends: average 32 days to pay, 30% of invoices not paid to agreed terms
18 months later
31 March 2023
Last accounts filed were made up to this date
11 months later
6 February 2024
Administration started
AccountsPayment reportInsolvency
Before it failed
Key figures
- Average days to pay suppliers, 1 April 2021 to 30 September 2021
- 32 days
- 5% paid after 60 days, 30% not paid to agreed terms
- Its last payment practices report
- Owed to unsecured creditors (estimated), as at 6 February 2024
- £26.1m
- of which trade creditors £6.0m. HMRC owed £6.2m. staff owed £1.7m. Expected return to unsecured creditors: none expected
- Administrators' proposals
The last accounts filed were full accounts made up to 31 March 2023, 10 months before it went into administration.
The full filing history, including any late filings, charges and director changes, is on Companies House.
Lessons learned report
We're writing plain-English reports on major construction failures: who was involved, why it happened, the warning signs and how long they were visible, and what to look out for next time.
Sign up to be told when reports are outIn the news
- Readie administration pays just £500k to HMRC
Construction News · 4 September 2026
- Readie administrators downgrade expectations
Construction News · 12 March 2026
- Readie administration extended by three years
Construction News · 6 January 2026
- Readie administration rumbles on without recovery from parent
Construction News · 6 March 2025
- Readie creditors’ losses rise by £17m
Construction News · 16 September 2024
- Readie supply chain hit for £24m
Construction News · 3 April 2024
- Readie collapse dominates February casualty list
Construction News · 11 March 2024
- Readie Construction topples into administration
Construction News · 7 February 2024