Administration · 8 January 2024
Stewart Milne Group
Main contractor · Aberdeen · Scotland · Part of Stewart Milne
What happened
STEWART MILNE GROUP LIMITED (company number SC057709), incorporated in 1975, entered administration on 8 January 2024. Its status at Companies House is now: administration.
Why it failed
Rising costs and falling housebuyer demand hurt trading; facing Bank of Scotland debt maturities, sale processes produced no deliverable deal and the group could not meet its debts.
- Main reason: Sale or investment failed
- Funding withdrawn
- Market downturn
- Cost inflation
Our summary of the reasons given in the administrators' proposals. These record the administrators' and directors' account of what happened.
An administrator, a licensed insolvency practitioner, takes control of the company to try to rescue it, sell the business or get a better result for creditors than a liquidation.
Timeline
The last accounts and payment report before the failure, then what happened, with the time between each.
31 October 2022
Last accounts filed were made up to this date
12 months later
31 October 2023
Last payment practices report ends: average 59 days to pay, 49% of invoices not paid to agreed terms
3 months later
8 January 2024
Administration started
AccountsPayment reportInsolvency
Before it failed
Key figures
- Average days to pay suppliers, 1 May 2023 to 31 October 2023
- 59 days
- 43% paid after 60 days, 49% not paid to agreed terms
- Its last payment practices report
- Owed to unsecured creditors (estimated), Administrators' proposals for Stewart Milne Group and its subsidiaries
- £153.9m
- about 1,375 creditors. HMRC owed £1.8m. a further £108.0m owed to its lenders. Expected return to unsecured creditors: about 0p in the pound
- Administrators' proposals for Stewart Milne Group and its subsidiaries
The last accounts filed were group accounts made up to 31 October 2022, 14 months before it went into administration.
The full filing history, including any late filings, charges and director changes, is on Companies House.
Lessons learned report
We're writing plain-English reports on major construction failures: who was involved, why it happened, the warning signs and how long they were visible, and what to look out for next time.
Sign up to be told when reports are outIn the news
- Stewart Milne administration extended by a year
Construction News · 13 January 2026
- Stewart Milne supply chain owed £153.8m
Construction News · 23 February 2024
- Stewart Milne in administration with hundreds of jobs lost
Construction News · 8 January 2024